Substation Scout

Phillips Island CT1, CT2, CT3, CT4

PJM queue ID T118

Queue IDT118
Project namePhillips Island CT1, CT2, CT3, CT4
Status (as published)In Service
SubstationLinwood
Point of interconnectionLinwood 230kV
CountyDelaware
StatePA
Voltage230 kV
Capacity10 MW
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operation2009-09-30
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy10
Mw Capacity10
Mfo840

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.