Vineland Unit #9 (S43) is listed in the PJM interconnection queue as a 17 MW project in Cumberland County, NJ. The filing names Vineland as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of November 12, 2007.
| Queue ID | S43 |
|---|---|
| Project name | Vineland Unit #9 |
| Status (as published) | In Service |
| Substation | Vineland |
| Point of interconnection | Vineland |
| County | Cumberland |
| State | NJ |
| Voltage | Not reported |
| Capacity | 17 MW |
| Resource (as published) | Oil |
| Resource category | Other (normalized for filtering) |
| Target commercial operation | 2007-11-12 |
| Source dataset | serial |
Same substation and county
Vineland substation: 4 requests in the PJM queue, 2 active totaling 80 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| S121 | Howard M. Down Power Plant Unit 11 | 63 | Gas | In Service |
| Y1-042 | Vineland 12kV | 1.3 | Solar | Withdrawn |
| X3-018 | Vineland 12kV | 0 | Solar | Withdrawn |
Cumberland, NJ: 94 requests in the PJM queue, 15 active totaling 1,148.7 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 17 |
| MW capacity | 17 |
| MFO | 17 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.