PJM queue ID R66

Marcal Paper (R66) is listed in the PJM interconnection queue as a 20 MW gas project in Bergen County, NJ. The filing names Fairlawn as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of May 1, 2009.

Queue IDR66
Project nameMarcal Paper
Status (as published)In Service
SubstationFairlawn
Point of interconnectionFairlawn 138kV
CountyBergen
StateNJ
Voltage138 kV
Capacity20 MW
Resource (as published)Natural Gas
Resource categoryGas (normalized for filtering)
Target commercial operation2009-05-01
Source datasetserial

Same substation and county

Fairlawn substation: 4 requests in the PJM queue, 1 active totaling 20 MW.

Queue IDProjectMWResourceStatus
C09Fairlawn 26.4kV37GasWithdrawn
W1-038Fairlawn 138kV10GasWithdrawn
X2-011Elmwood6GasDeactivated

Bergen, NJ: 39 requests in the PJM queue, 16 active totaling 1,069.5 MW.

A substation with the same name is named in PJM transmission planning materials: Fairlawn (PSEG, 2 mentions).

Same name and state (weaker). Matched on name and state: the utility that presented this substation operates in one state, and every queue filing at a substation of the same name is in that state. No transmission owner is recorded on those filings, so this is a weaker match than one on owner. Not verified as the same facility.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy20
MW capacity20
MFO67

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first