Cook #1
PJM queue ID O42
Cook #1 (O42) is listed in the PJM interconnection queue as a 84 MW nuclear project in Berrien County, MI. The filing names Cook as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of January 19, 2007.
| Queue ID | O42 |
|---|---|
| Project name | Cook #1 |
| Status (as published) | In Service |
| Substation | Cook |
| Point of interconnection | Cook 345 kV |
| County | Berrien |
| State | MI |
| Voltage | 345 kV |
| Capacity | 84 MW |
| Resource (as published) | Nuclear |
| Resource category | Nuclear (normalized for filtering) |
| Target commercial operation | 2007-01-19 |
| Source dataset | serial |
Same substation and county
Cook substation: 2 requests in the PJM queue, 1 active totaling 84 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| N46 | Cook 345kV | 1,120 | Gas | Withdrawn |
Berrien, MI: 20 requests in the PJM queue, 15 active totaling 1,301 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 84 |
| MW capacity | 84 |
| MFO | 1100 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.