Pittsylvania
PJM queue ID O06_DP01
Pittsylvania (O06_DP01) is listed in the PJM interconnection queue as a 4 MW project in Pittsylvania County, VA. The filing names Altavista as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of June 1, 2006.
| Queue ID | O06_DP01 |
|---|---|
| Project name | Pittsylvania |
| Status (as published) | In Service |
| Substation | Altavista |
| Point of interconnection | Altavista 115kV |
| County | Pittsylvania |
| State | VA |
| Voltage | 115 kV |
| Capacity | 4 MW |
| Resource (as published) | Wood |
| Resource category | Other (normalized for filtering) |
| Target commercial operation | 2006-06-01 |
| Source dataset | serial |
Same substation and county
Altavista substation: 2 requests in the PJM queue, 2 active totaling 64 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| X1-084 | Altavista Power Station | 60 | Other | In Service |
Pittsylvania, VA: 39 requests in the PJM queue, 14 active totaling 751.1 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 4 |
| MW capacity | 4 |
| MFO | 83.6 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.