Southern Landfill Units 1-4 (N17) is listed in the PJM interconnection queue as a 3 MW gas project in New Castle County, DE. The filing names Laurel-Sussex as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of October 24, 2006.

Queue IDN17
Project nameSouthern Landfill Units 1-4
Status (as published)In Service
SubstationLaurel-Sussex
Point of interconnectionLaurel-Sussex 69kV
CountyNew Castle
StateDE
Voltage69 kV
Capacity3 MW
Resource (as published)Methane
Resource categoryGas (normalized for filtering)
Target commercial operation2006-10-24
Source datasetserial

Same substation and county

Laurel-Sussex substation: 3 requests in the PJM queue, 2 active totaling 8 MW.

Queue IDProjectMWResourceStatus
T11Southern LF Units 1-55GasIn Service
AF1-157Laurel-Sussex 69 kV15SolarWithdrawn

New Castle, DE: 65 requests in the PJM queue, 31 active totaling 1,405.6 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy3
MFO3

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first