Backbone WF
PJM queue ID K19
Backbone WF (K19) is listed in the PJM interconnection queue as a 18 MW wind project in Tucker County, WV. The filing names Backbone Mountain as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of June 1, 2001.
| Queue ID | K19 |
|---|---|
| Project name | Backbone WF |
| Status (as published) | In Service |
| Substation | Backbone Mountain |
| Point of interconnection | Backbone Mountain 138kV |
| County | Tucker |
| State | WV |
| Voltage | 138 kV |
| Capacity | 18 MW |
| Resource (as published) | Wind |
| Resource category | Wind (normalized for filtering) |
| Target commercial operation | 2001-06-01 |
| Source dataset | serial |
Same substation and county
Backbone Mountain substation: 4 requests in the PJM queue, 2 active totaling 36 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| B28_W07 | Backbone WF | 18 | Wind | In Service |
| AD2-126 | Backbone Mountain 138 kV | 18 | Battery | Withdrawn |
| AA2-103 | Backbone Mountain Energy Storage | 0 | Battery | Withdrawn |
Tucker, WV: 10 requests in the PJM queue, 3 active totaling 94.7 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 0 |
| MW capacity | 18 |
| MFO | 90 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.