PJM queue ID K19

Backbone WF (K19) is listed in the PJM interconnection queue as a 18 MW wind project in Tucker County, WV. The filing names Backbone Mountain as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of June 1, 2001.

Queue IDK19
Project nameBackbone WF
Status (as published)In Service
SubstationBackbone Mountain
Point of interconnectionBackbone Mountain 138kV
CountyTucker
StateWV
Voltage138 kV
Capacity18 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Target commercial operation2001-06-01
Source datasetserial

Same substation and county

Backbone Mountain substation: 4 requests in the PJM queue, 2 active totaling 36 MW.

Queue IDProjectMWResourceStatus
B28_W07Backbone WF18WindIn Service
AD2-126Backbone Mountain 138 kV18BatteryWithdrawn
AA2-103Backbone Mountain Energy Storage0BatteryWithdrawn

Tucker, WV: 10 requests in the PJM queue, 3 active totaling 94.7 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy0
MW capacity18
MFO90

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first