Substation Scout

Neptune

PJM queue ID G07_MTX1

Neptune (G07_MTX1) is listed in the PJM interconnection queue as a merchant transmission request for 790 MW in Middlesex County, NJ. The filing names Sayreville as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of June 30, 2007.

Queue IDG07_MTX1
Project nameNeptune
Status (as published)In Service
SubstationSayreville
Point of interconnectionSayreville 230kV
CountyMiddlesex
StateNJ
Voltage230 kV
Capacity790 MW
Resource (as published)Not reported
Resource categoryNot reported (normalized for filtering)
Target commercial operation2007-06-30
Source datasetserial

Same substation and county

Sayreville substation: 8 requests in the PJM queue, 2 active totaling 1,555 MW.

Queue IDProjectMWResourceStatus
A15Red Oak CC1, CT1 - CT4765GasIn Service
A37Sayreville 230 kV749GasWithdrawn
X3-089Sayreville 230kV744GasWithdrawn
J08_MTX14Sayreville 230kV80Not reportedWithdrawn
E16Sayreville 230kV70GasWithdrawn
AC1-026Sayreville0BatteryWithdrawn
S68Sayreville 230kV0Not reportedWithdrawn

Middlesex, NJ: 120 requests in the PJM queue, 33 active totaling 4,764.7 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeMerchant Transmission
MW energy790
MFO790

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first