Substation Scout

Columbia DP 115 kV

PJM queue ID C01-2128

Columbia DP 115 kV (C01-2128) is listed in the PJM interconnection queue as a 12 MW solar project in Goochland County, VA. The filing names Columbia DP as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of May 20, 2027.

Queue IDC01-2128
Project nameColumbia DP 115 kV
Status (as published)Active
SubstationColumbia DP
Point of interconnectionColumbia DP 115 kV
CountyGoochland
StateVA
Voltage115 kV
Capacity12 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2027-05-20
Source datasetcycle

Same substation and county

Columbia DP substation: 3 requests in the PJM queue, 1 active totaling 12 MW.

Queue IDProjectMWResourceStatus
AH1-170Horsepen Creek Solar I12SolarWithdrawn
AH1-171Columbia DP 115kV12SolarWithdrawn

Goochland, VA: 6 requests in the PJM queue, 1 active totaling 12 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperHorsepen Creek Solar, LLC
Transmission ownerDominion
Project typeGeneration Interconnection
CycleC01
StagePhase 1
MW energy20.0
MW capacity12.0
MFO40.0
Submitted date4/27/2026
Last updated6/23/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first