Dumont - Greentown 765 kV
PJM queue ID C01-2020
Dumont - Greentown 765 kV (C01-2020) is listed in the PJM interconnection queue as a 931.1 MW gas project in Marshall County, IN. The filing names Dumont - Greentown as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of May 31, 2031.
| Queue ID | C01-2020 |
|---|---|
| Project name | Dumont - Greentown 765 kV |
| Status (as published) | Active |
| Substation | Dumont - Greentown |
| Point of interconnection | Dumont - Greentown 765 kV |
| County | Marshall |
| State | IN |
| Voltage | 765 kV |
| Capacity | 931.1 MW |
| Resource (as published) | Natural Gas |
| Resource category | Gas (normalized for filtering) |
| Target commercial operation | 2031-05-31 |
| Source dataset | cycle |
Same substation and county
Dumont - Greentown substation: 4 requests in the PJM queue, 1 active totaling 931.1 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| C01-2023 | Dumont - Greentown 765 kV | 931.1 | Gas | Withdrawn |
| AG2-330 | Dumont - Greentown 765 kV | 156 | Battery | Withdrawn |
| AG2-328 | Dumont - Greentown 765 kV | 26 | Solar | Withdrawn |
Marshall, IN: 8 requests in the PJM queue, 1 active totaling 931.1 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Developer | Cortex Sycamore, LLC |
|---|---|
| Transmission owner | AEP |
| Project type | Generation Interconnection |
| Cycle | C01 |
| Stage | Phase 1 |
| MW energy | 976.1 |
| MW capacity | 931.1 |
| MFO | 976.1 |
| Submitted date | 4/26/2026 |
| Last updated | 6/25/2026 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.