Oyster Creek 230 kV (C01-1937) is listed in the PJM interconnection queue as a 35 MW battery project in Ocean County, NJ. The filing names Oyster Creek as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of January 1, 2028.

Queue IDC01-1937
Project nameOyster Creek 230 kV
Status (as published)Active
SubstationOyster Creek
Point of interconnectionOyster Creek 230 kV
CountyOcean
StateNJ
Voltage230 kV
Capacity35 MW
Resource (as published)Storage
Resource categoryBattery (normalized for filtering)
Target commercial operation2028-01-01
Source datasetcycle

Same substation and county

Oyster Creek substation: 6 requests in the PJM queue, 1 active totaling 35 MW.

Queue IDProjectMWResourceStatus
B04Oyster Creek800GasWithdrawn
A45Oyster Creek 230 kV752GasWithdrawn
AE1-020Ocean Wind229.3Offshore WindPending Termination
AI2-325Oyster Creek 230 kV178.7Offshore WindWithdrawn
AA1-097Oyster Creek 230kV100GasWithdrawn

Ocean, NJ: 55 requests in the PJM queue, 15 active totaling 653.1 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperPearl Storage LLC
Transmission ownerJCPL
Project typeGeneration Interconnection
CycleC01
StagePhase 1
MW energy35.0
MW capacity35.0
MFO100.0
Submitted date4/27/2026
Last updated6/2/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first