Substation Scout

Broadford 138 kV

PJM queue ID C01-1842

Queue IDC01-1842
Project nameBroadford 138 kV
Status (as published)Active
SubstationBroadford
Point of interconnectionBroadford 138 kV
CountySmyth
StateVA
Voltage138 kV
Capacity375 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2032-03-01
Source datasetcycle

Additional filed fields

DeveloperLaurel Creek Energy Storage II LLC
Transmission OwnerAEP
Project TypeGeneration Interconnection
CycleC01
StagePhase 1
Mw Energy375.0
Mw Capacity375.0
Mfo375.0
Submitted Date4/24/2026
Last Updated6/4/2026