Broadford substation interconnection queue

2 active projects totalling 625 MW in the PJM queue, plus 1 with terminal status (shown greyed).

2active projects
625active MW
3total filed
Queue IDProjectkVMWResourceStatus
C01-1842 Broadford 138 kV 138 375 Battery Active
AG2-360 Broadford 138 kV 138 250 Battery Active
AG2-597 Broadford 138 kV 138 120 Hybrid Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.