Substation Scout

Landis 138 kV

PJM queue ID C01-1769

Queue IDC01-1769
Project nameLandis 138 kV
Status (as published)Active
SubstationLandis
Point of interconnectionLandis 138 kV
CountyCumberland
StateNJ
Voltage138 kV
Capacity325 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2030-12-31
Source datasetcycle

Additional filed fields

DeveloperZenobe Vineland, LLC
Transmission OwnerAEC
Project TypeGeneration Interconnection
CycleC01
StagePhase 1
Mw Energy325.0
Mw Capacity325.0
Mfo325.0
Submitted Date4/27/2026
Last Updated6/30/2026