Substation Scout

Cole Road 345 kV

PJM queue ID C01-1657

Cole Road 345 kV (C01-1657) is listed in the PJM interconnection queue as a 40 MW solar project in Franklin County, OH. The filing names Cole Road as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of April 24, 2028.

Queue IDC01-1657
Project nameCole Road 345 kV
Status (as published)Active
SubstationCole Road
Point of interconnectionCole Road 345 kV
CountyFranklin
StateOH
Voltage345 kV
Capacity40 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2028-04-24
Source datasetcycle

Same substation and county

Cole Road substation: 2 requests in the PJM queue, 1 active totaling 40 MW.

Queue IDProjectMWResourceStatus
AI2-171Cole Road 345 kV40SolarWithdrawn

Franklin, OH: 20 requests in the PJM queue, 5 active totaling 218 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperPleasant Prairie Solar Energy LLC
Transmission ownerAEP
Project typeGeneration Interconnection
CycleC01
StagePhase 1
MW energy0.0
MW capacity40.0
MFO240.0
Submitted date4/26/2026
Last updated6/23/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.