Cheltenham 500 kV
PJM queue ID C01-1494
Cheltenham 500 kV (C01-1494) is listed in the PJM interconnection queue as a 618 MW gas project in Prince George's County, MD. The filing names Cheltenham as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of April 15, 2031.
| Queue ID | C01-1494 |
|---|---|
| Project name | Cheltenham 500 kV |
| Status (as published) | Active |
| Substation | Cheltenham |
| Point of interconnection | Cheltenham 500 kV |
| County | Prince George's |
| State | MD |
| Voltage | 500 kV |
| Capacity | 618 MW |
| Resource (as published) | Natural Gas |
| Resource category | Gas (normalized for filtering) |
| Target commercial operation | 2031-04-15 |
| Source dataset | cycle |
Same substation and county
Cheltenham substation: 4 requests in the PJM queue, 4 active totaling 1,266.3 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| C01-1268 | Cheltenham 500 kV | 400 | Battery | Active |
| C01-1132 | Cheltenham 500 kV | 200 | Battery | Active |
| AH1-744 | PARKWAY GENERATION OPERATING LLC | 48.3 | Gas | EP |
Prince George's, MD: 57 requests in the PJM queue, 14 active totaling 3,551.2 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Developer | Parkway Generation Operating, LLC |
|---|---|
| Transmission owner | PEPCO |
| Project type | Generation Interconnection |
| Cycle | C01 |
| Stage | Phase 1 |
| MW energy | 618.0 |
| MW capacity | 618.0 |
| MFO | 618.0 |
| Submitted date | 4/27/2026 |
| Last updated | 6/24/2026 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.