Queue IDC01-1397
Project nameMickelton 230 kV
Status (as published)Active
SubstationMickelton
Point of interconnectionMickelton 230 kV
CountyGloucester
StateNJ
Voltage230 kV
Capacity44 MW
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operation2027-06-01
Source datasetcycle

Additional filed fields

DeveloperWest Deptford Energy, LLC
Transmission OwnerAEC
Project TypeGeneration Interconnection
CycleC01
StagePhase 1
Mw Energy0.0
Mw Capacity44.0
Mfo850.0
Submitted Date4/24/2026
Last Updated6/23/2026