Substation Scout

Chicago Heights 138kV 138 kV

PJM queue ID C01-1334

Chicago Heights 138kV 138 kV (C01-1334) is listed in the PJM interconnection queue as a 250 MW battery project in Cook County, IL. The filing names Chicago Heights as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of June 1, 2031.

Queue IDC01-1334
Project nameChicago Heights 138kV 138 kV
Status (as published)Active
SubstationChicago Heights
Point of interconnectionChicago Heights 138kV 138 kV
CountyCook
StateIL
Voltage138 kV
Capacity250 MW
Resource (as published)Storage
Resource categoryBattery (normalized for filtering)
Target commercial operation2031-06-01
Source datasetcycle

Same substation and county

Chicago Heights substation: 5 requests in the PJM queue, 1 active totaling 250 MW.

Queue IDProjectMWResourceStatus
AH1-616Chicago Heights 138 kV150BatteryWithdrawn
AI1-155Chicago Heights 138kV110BatteryWithdrawn
O12Geneva Energy LLC20OtherDeactivated
AC1-169Chicago Heights0SolarWithdrawn

Cook, IL: 45 requests in the PJM queue, 9 active totaling 1,488.4 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperLincoln Reserve Energy, LLC
Transmission ownerComEd
Project typeGeneration Interconnection
CycleC01
StagePhase 1
MW energy250.0
MW capacity250.0
MFO250.0
Submitted date4/27/2026
Last updated6/19/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.