Substation Scout

LaSalle 345 kV

PJM queue ID C01-1260

LaSalle 345 kV (C01-1260) is listed in the PJM interconnection queue as a 170.8 MW nuclear project in LaSalle County, IL. The filing names LaSalle as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of March 23, 2030.

Queue IDC01-1260
Project nameLaSalle 345 kV
Status (as published)Active
SubstationLaSalle
Point of interconnectionLaSalle 345 kV
CountyLaSalle
StateIL
Voltage345 kV
Capacity170.8 MW
Resource (as published)Nuclear
Resource categoryNuclear (normalized for filtering)
Target commercial operation2030-03-23
Source datasetcycle

Same substation and county

LaSalle substation: 8 requests in the PJM queue, 4 active totaling 584 MW.

Queue IDProjectMWResourceStatus
C01-1571LaSalle 345 kV346GasActive
P10Grand Ridge WF37.2WindIn Service
N15Grand Ridge Energy LLC30WindIn Service
W1-040LaSalle350NuclearWithdrawn
Y1-005LaSalle350NuclearWithdrawn
AI2-178LaSalle 138 kV36.5WindWithdrawn
AI2-180LaSalle 138kV6.2WindWithdrawn

LaSalle, IL: 5 requests in the PJM queue, 4 active totaling 559.5 MW.

A substation with the same name is named in PJM transmission planning materials: LaSalle (COMED, 4 mentions).

Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperConstellation Energy Generation, LLC
Transmission ownerComEd
Project typeGeneration Interconnection
CycleC01
StagePhase 1
MW energy180.0
MW capacity170.8
MFO1368.0
Submitted date4/24/2026
Last updated6/4/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first