Substation Scout

Amos 345 kV

PJM queue ID C01-1204

Amos 345 kV (C01-1204) is listed in the PJM interconnection queue as a 10 MW coal project in Putnam County, WV. The filing names Amos as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of June 25, 2026.

Queue IDC01-1204
Project nameAmos 345 kV
Status (as published)Active
SubstationAmos
Point of interconnectionAmos 345 kV
CountyPutnam
StateWV
Voltage345 kV
Capacity10 MW
Resource (as published)Coal
Resource categoryCoal (normalized for filtering)
Target commercial operation2026-06-25
Source datasetcycle

Same substation and county

Amos substation: 3 requests in the PJM queue, 3 active totaling 33.1 MW.

Queue IDProjectMWResourceStatus
C01-1035Amos 765 kV13.1CoalActive
C01-1188Amos 765 kV10CoalActive

Putnam, WV: 5 requests in the PJM queue, 4 active totaling 69.1 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperAppalachian Power Company
Transmission ownerAEP
Project typeGeneration Interconnection
CycleC01
StagePhase 1
MW energy10.0
MW capacity10.0
MFO810.0
Submitted date4/23/2026
Last updated6/24/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.