Amos 765 kV

PJM queue ID C01-1035

Queue IDC01-1035
Project nameAmos 765 kV
Status (as published)Active
SubstationAmos
Point of interconnectionAmos 765 kV
CountyPutnam
StateWV
Voltage765 kV
Capacity13.1 MW
Resource (as published)Coal
Resource categoryCoal (normalised for filtering)
Target commercial operation2026-04-01
Source datasetcycle

Additional filed fields

DeveloperAppalachian Power Company
Transmission OwnerAEP
Project TypeGeneration Interconnection
CycleC01
StagePhase 1
Mw Energy0.0
Mw Capacity13.1
Mfo1336.0
Submitted Date4/23/2026
Last Updated6/24/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.