Gans 8 & 9 (B23_W04) is listed in the PJM interconnection queue as a 88 MW gas project in Fayette County, PA. The filing names Gans as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of December 1, 2001.

Queue IDB23_W04
Project nameGans 8 & 9
Status (as published)In Service
SubstationGans
Point of interconnectionGans 138 kV
CountyFayette
StatePA
Voltage138 kV
Capacity88 MW
Resource (as published)Natural Gas
Resource categoryGas (normalized for filtering)
Target commercial operation2001-12-01
Source datasetserial

Same substation and county

Gans substation: 4 requests in the PJM queue, 2 active totaling 98.1 MW.

Queue IDProjectMWResourceStatus
N32South Chestnut WF10.1WindIn Service
AD2-109Gans 138kV12GasWithdrawn
AG1-516Gans Energy CT and BESS4BatteryWithdrawn

Fayette, PA: 56 requests in the PJM queue, 20 active totaling 6,162.5 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy88
MW capacity88
MFO88

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first