Substation Scout

Cunningham 500 kV

PJM queue ID AH1-681

Queue IDAH1-681
Project nameCunningham 500 kV
Status (as published)Active
SubstationCunningham
Point of interconnectionCunningham 500 kV
CountyFluvanna
StateVA
Voltage500 kV
Capacity27.3 MW
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operationNot reported
Source datasetcycle

Additional filed fields

DeveloperTenaska Virginia Partners, L.P.
Transmission OwnerDominion
Project TypeGeneration Interconnection
CycleTC2
StagePHASE 2
Mw Energy0.0
Mw Capacity27.3
Mfo1000.0
Submitted Date6/3/2025
Last Updated5/14/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.