Derry Tap-Derry Bus 69 kV III (AG2-481) is listed in the PJM interconnection queue as a 4.1 MW solar project in Northumberland County, PA. The filing names Derry Tap-Derry Bus III as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of March 31, 2027.

Queue IDAG2-481
Project nameDerry Tap-Derry Bus 69 kV III
Status (as published)Active
SubstationDerry Tap-Derry Bus III
Point of interconnectionDerry Tap-Derry Bus 69 kV III
CountyNorthumberland
StatePA
Voltage69 kV
Capacity4.1 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2027-03-31
Source datasetcycle

Same substation and county

Derry Tap-Derry Bus III substation: 2 requests in the PJM queue, 1 active totaling 4.1 MW.

Queue IDProjectMWResourceStatus
AH1-469Derry Tap-Derry Bus 69 kV III15HybridWithdrawn

Northumberland, PA: 36 requests in the PJM queue, 7 active totaling 129.7 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperCottontail Solar 4, LLC
Transmission ownerPPL
Project typeGeneration Interconnection
CycleTC2
StagePhase 3
MW energy0.0
MW capacity4.1
MFO20.0
Submitted date3/31/2021
Last updated8/21/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.