Continental 69 kV (AG2-405) is listed in the PJM interconnection queue as a 11 MW solar project in Putnam County, OH. The filing names Continental as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of December 2, 2025.
| Queue ID | AG2-405 |
|---|---|
| Project name | Continental 69 kV |
| Status (as published) | Active |
| Substation | Continental |
| Point of interconnection | Continental 69 kV |
| County | Putnam |
| State | OH |
| Voltage | 69 kV |
| Capacity | 11 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2025-12-02 |
| Source dataset | cycle |
Same substation and county
Continental substation: 3 requests in the PJM queue, 2 active totaling 30 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| AD1-101 | Blue Harvest Solar Park | 19 | Solar | In Service |
| AI2-118 | Continental 69 kV | 12 | Solar | Withdrawn |
Putnam, OH: 10 requests in the PJM queue, 4 active totaling 169 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Developer | Blue Harvest Solar Park LLC |
|---|---|
| Transmission owner | AEP |
| Project type | Generation Interconnection |
| Cycle | TC2 |
| Stage | Phase 3 |
| MW energy | 0.0 |
| MW capacity | 10.98 |
| MFO | 49.9 |
| Submitted date | 3/30/2021 |
| Last updated | 8/31/2026 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.