Turner 34.5 kV

PJM queue ID AG2-193

Queue IDAG2-193
Project nameTurner 34.5 kV
Status (as published)Active
SubstationTurner
Point of interconnectionTurner 34.5 kV
CountyHenrico
StateVA
Voltage34.5 kV
Capacity12 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2026-07-03
Source datasetcycle

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperVirginia Electric and Power Company (d/b/a Dominion Energy Virginia)
Transmission OwnerDominion
Project TypeGeneration Interconnection
CycleTC2
StagePhase 3
Mw Energy20.0
Mw Capacity12.0
Mfo20.0
Submitted Date2/27/2021
Last Updated8/18/2026