Franklintown Farm Solar and BESS
PJM queue ID AG1-307
Franklintown Farm Solar and BESS (AG1-307) is listed in the PJM interconnection queue as a 56 MW hybrid project in Jefferson County, WV. The filing names Old Chapel-Millville as its point of interconnection. PJM lists its status as “Engineering and Procurement”, with a target commercial operation date of July 30, 2028.
| Queue ID | AG1-307 |
|---|---|
| Project name | Franklintown Farm Solar and BESS |
| Status (as published) | Engineering and Procurement |
| Substation | Old Chapel-Millville |
| Point of interconnection | Old Chapel-Millville 138 kV |
| County | Jefferson |
| State | WV |
| Voltage | 138 kV |
| Capacity | 56 MW |
| Resource (as published) | Solar; Storage |
| Resource category | Hybrid (normalized for filtering) |
| Target commercial operation | 2028-07-30 |
| Source dataset | serial |
Same substation and county
Old Chapel-Millville substation: 5 requests in the PJM queue, 1 active totaling 56 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| AD2-158 | Wild Hill Solar | 46.5 | Solar | Withdrawn |
| AI2-375 | Old Chapel-Millville 138 kV | 24 | Solar | Withdrawn |
| AG1-097 | Old Chapel-Millville 138 kV | 13 | Solar | Withdrawn |
| AD1-158 | Old Chapel-Millville 138kV | 12 | Solar | Withdrawn |
Jefferson, WV: 15 requests in the PJM queue, 5 active totaling 259.3 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 80 |
| MW capacity | 56 |
| MFO | 80 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.