Substation Scout

Riverbank Energy

PJM queue ID AF2-441

Queue IDAF2-441
Project nameRiverbank Energy
Status (as published)EP
SubstationBurnham
Point of interconnectionBurnham 138kV
CountyCook
StateIL
Voltage138 kV
Capacity80 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2030-05-31
Source datasetcycle

Additional filed fields

DeveloperLincoln Reserve Energy, LLC
Transmission OwnerComEd
Project TypeGeneration Interconnection
CycleTC1
StageFINAL AGREEMENT
Mw Energy200.0
Mw Capacity80.0
Mfo200.0
Submitted Date3/31/2020
Last Updated2/4/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.