Frosty Valley Energy Center
PJM queue ID AF2-434
Frosty Valley Energy Center (AF2-434) is listed in the PJM interconnection queue as a 12 MW solar project in Columbia County, PA. The filing names Columbia-Geisinger Tap #1 as its point of interconnection. PJM lists its status as “Engineering and Procurement”, with a target commercial operation date of January 15, 2028.
| Queue ID | AF2-434 |
|---|---|
| Project name | Frosty Valley Energy Center |
| Status (as published) | Engineering and Procurement |
| Substation | Columbia-Geisinger Tap #1 |
| Point of interconnection | Columbia-Geisinger Tap #1 69 kV |
| County | Columbia |
| State | PA |
| Voltage | 69 kV |
| Capacity | 12 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2028-01-15 |
| Source dataset | serial |
Same substation and county
Columbia-Geisinger Tap #1 substation: 2 requests in the PJM queue, 2 active totaling 24 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| AF2-433 | Frosty Valley Energy Center | 12 | Solar | Engineering and Procurement |
Columbia, PA: 35 requests in the PJM queue, 10 active totaling 135.3 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 20 |
| MW capacity | 12 |
| MFO | 40 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.