Substation Scout

FLR Florence Landfill

PJM queue ID AF2-247

FLR Florence Landfill (AF2-247) is listed in the PJM interconnection queue as a 2.1 MW solar project in Burlington County, NJ. The filing names Bustleton as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of June 30, 2022.

Queue IDAF2-247
Project nameFLR Florence Landfill
Status (as published)In Service
SubstationBustleton
Point of interconnectionBustleton 13.2 kV
CountyBurlington
StateNJ
Voltage13.2 kV
Capacity2.1 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2022-06-30
Source datasetserial

Same substation and county

Bustleton substation: 5 requests in the PJM queue, 1 active totaling 2.1 MW.

Queue IDProjectMWResourceStatus
J04Bustleton 138kV7GasWithdrawn
AE2-016Bustleton 13.2 kV2.4SolarWithdrawn
AG2-422Burlington Energy Storage0HybridWithdrawn
X3-007LB Solar0SolarWithdrawn

Burlington, NJ: 118 requests in the PJM queue, 31 active totaling 656.5 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy5
MW capacity2.1
MFO5

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.