Currituck Solar
PJM queue ID AF2-081
Currituck Solar (AF2-081) is listed in the PJM interconnection queue as a 56 MW solar project in Currituck County, NC. The filing names Moyock as its point of interconnection. PJM lists its status as “EP”, with a target commercial operation date of March 31, 2031.
| Queue ID | AF2-081 |
|---|---|
| Project name | Currituck Solar |
| Status (as published) | EP |
| Substation | Moyock |
| Point of interconnection | Moyock 230 kV |
| County | Currituck |
| State | NC |
| Voltage | 230 kV |
| Capacity | 56 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2031-03-31 |
| Source dataset | cycle |
Same substation and county
Moyock substation: 2 requests in the PJM queue, 1 active totaling 56 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| AI1-169 | Moyock 230 kV | 26.4 | Hybrid | Withdrawn |
Currituck, NC: 17 requests in the PJM queue, 5 active totaling 305.9 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Developer | Currituck Solar, LLC |
|---|---|
| Transmission owner | Dominion |
| Project type | Generation Interconnection |
| Cycle | TC1 |
| Stage | FINAL AGREEMENT |
| MW energy | 80.0 |
| MW capacity | 56.0 |
| MFO | 80.0 |
| Submitted date | 1/31/2020 |
| Last updated | 6/18/2026 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.