Zion Energy Center - BESS

PJM queue ID AF2-027

Zion Energy Center - BESS (AF2-027) is listed in the PJM interconnection queue as a 20 MW battery project in Lake County, IL. The filing names Zion Energy Center as its point of interconnection. PJM lists its status as “Engineering and Procurement”, with a target commercial operation date of July 2, 2029.

Queue IDAF2-027
Project nameZion Energy Center - BESS
Status (as published)Engineering and Procurement
SubstationZion Energy Center
Point of interconnectionZion Energy Center 345 kV
CountyLake
StateIL
Voltage345 kV
Capacity20 MW
Resource (as published)Storage
Resource categoryBattery (normalized for filtering)
Target commercial operation2029-07-02
Source datasetserial

Same substation and county

Zion Energy Center substation: 4 requests in the PJM queue, 2 active totaling 110 MW.

Queue IDProjectMWResourceStatus
Y3-013Zion Energy Center90GasIn Service
Y2-103Zion Energy Center360GasWithdrawn
AH1-045Zion Energy Center 345 kV13.8SolarWithdrawn

Lake, IL: 20 requests in the PJM queue, 7 active totaling 1,360 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy50
MW capacity20
MFO635

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.