Substation Scout

Clermont County Solar Project

PJM queue ID AF1-045

Clermont County Solar Project (AF1-045) is listed in the PJM interconnection queue as a 31.3 MW battery project in Clermont County, OH. The filing names Cedarville-Ford as its point of interconnection. PJM lists its status as “Suspended”, with a target commercial operation date of December 31, 2025.

Queue IDAF1-045
Project nameClermont County Solar Project
Status (as published)Suspended
SubstationCedarville-Ford
Point of interconnectionCedarville-Ford 138 kV
CountyClermont
StateOH
Voltage138 kV
Capacity31.3 MW
Resource (as published)Storage
Resource categoryBattery (normalized for filtering)
Target commercial operation2025-12-31
Source datasetserial

Same substation and county

Cedarville-Ford substation: 3 requests in the PJM queue, 1 active totaling 31.3 MW.

Queue IDProjectMWResourceStatus
AE2-329Cedarville-Ford 138 kV208.8BatteryWithdrawn
AF1-315Cedarville-Ford 138 kV36SolarWithdrawn

Clermont, OH: 23 requests in the PJM queue, 8 active totaling 1,194.6 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy52.2
MW capacity31.3
MFO152.2

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.