Clermont County Solar Project (AE2-318) is listed in the PJM interconnection queue as a 67.2 MW solar project in Clermont County, OH. The filing names Ford-Cedarville as its point of interconnection. PJM lists its status as “Suspended”, with a target commercial operation date of December 31, 2025.
| Queue ID | AE2-318 |
|---|---|
| Project name | Clermont County Solar Project |
| Status (as published) | Suspended |
| Substation | Ford-Cedarville |
| Point of interconnection | Ford-Cedarville 138 kV |
| County | Clermont |
| State | OH |
| Voltage | 138 kV |
| Capacity | 67.2 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2025-12-31 |
| Source dataset | serial |
Same substation and county
Ford-Cedarville substation: 2 requests in the PJM queue, 1 active totaling 67.2 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| AG2-118 | Ford-Cedarville 138 kV | 56.2 | Solar | Withdrawn |
Clermont, OH: 23 requests in the PJM queue, 8 active totaling 1,194.6 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 100 |
| MW capacity | 67.2 |
| MFO | 100 |