Substation Scout

Squab Solar

PJM queue ID AE2-316

Squab Solar (AE2-316) is listed in the PJM interconnection queue as a 41.2 MW solar project in Jefferson County, PA. The filing names Brookville-Squab Hollow as its point of interconnection. PJM lists its status as “Under Construction”, with a target commercial operation date of July 10, 2027.

Queue IDAE2-316
Project nameSquab Solar
Status (as published)Under Construction
SubstationBrookville-Squab Hollow
Point of interconnectionBrookville-Squab Hollow 138 kV
CountyJefferson
StatePA
Voltage138 kV
Capacity41.2 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2027-07-10
Source datasetserial

Same substation and county

Brookville-Squab Hollow substation: 2 requests in the PJM queue, 2 active totaling 59.2 MW.

Queue IDProjectMWResourceStatus
AF1-302Squab Solar18SolarUnder Construction

Jefferson, PA: 11 requests in the PJM queue, 3 active totaling 79.2 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy90
MW capacity41.2
MFO90

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first