Hillandale Solar (AE2-291) is listed in the PJM interconnection queue as a 61.2 MW solar project in Pittsylvania County, VA. The filing names Grit DP-Perth as its point of interconnection. PJM lists its status as “EP”, with a target commercial operation date of May 28, 2030.
| Queue ID | AE2-291 |
|---|---|
| Project name | Hillandale Solar |
| Status (as published) | EP |
| Substation | Grit DP-Perth |
| Point of interconnection | Grit DP-Perth 115 kV |
| County | Pittsylvania |
| State | VA |
| Voltage | 115 kV |
| Capacity | 61.2 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2030-05-28 |
| Source dataset | cycle |
Same substation and county
Grit DP-Perth substation: 3 requests in the PJM queue, 1 active totaling 61.2 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| AE2-292 | Grit DP-Perth 115 kV | 76.2 | Solar | Withdrawn |
| AG1-539 | Grit DP-Perth 115 kV | 32 | Battery | Withdrawn |
Pittsylvania, VA: 39 requests in the PJM queue, 14 active totaling 751.1 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Developer | Hillandale Solar, LLC |
|---|---|
| Transmission owner | Dominion |
| Project type | Generation Interconnection |
| Cycle | TC1 |
| Stage | FINAL AGREEMENT |
| MW energy | 102.0 |
| MW capacity | 61.2 |
| MFO | 102.0 |
| Submitted date | 3/29/2019 |
| Last updated | 10/14/2026 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.