Substation Scout

Blairs Valley

PJM queue ID AE2-054

Blairs Valley (AE2-054) is listed in the PJM interconnection queue as a 12 MW solar project in Franklin County, PA. The filing names Warfordsburg as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of November 30, 2024.

Queue IDAE2-054
Project nameBlairs Valley
Status (as published)In Service
SubstationWarfordsburg
Point of interconnectionWarfordsburg 34 kV
CountyFranklin
StatePA
Voltage34 kV
Capacity12 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2024-11-30
Source datasetserial

Same substation and county

Warfordsburg substation: 2 requests in the PJM queue, 1 active totaling 12 MW.

Queue IDProjectMWResourceStatus
AG2-374Warfordsburg 12 kV3SolarWithdrawn

Franklin, PA: 80 requests in the PJM queue, 20 active totaling 384.3 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy20
MW capacity12
MFO20

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.