Substation Scout

Blackwater Solar

PJM queue ID AE1-173

Blackwater Solar (AE1-173) is listed in the PJM interconnection queue as a 480 MW solar project in Sussex County, VA. The filing names Carson-Suffolk as its point of interconnection. PJM lists its status as “Under Construction”, with a target commercial operation date of October 1, 2030.

Queue IDAE1-173
Project nameBlackwater Solar
Status (as published)Under Construction
SubstationCarson-Suffolk
Point of interconnectionCarson-Suffolk 500 kV
CountySussex
StateVA
Voltage500 kV
Capacity480 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2030-10-01
Source datasetserial

Same substation and county

Carson-Suffolk substation: 4 requests in the PJM queue, 1 active totaling 480 MW.

Queue IDProjectMWResourceStatus
AG1-178Carson-Suffolk 500 kV324.9SolarWithdrawn
AH2-150Carson-Suffolk 500 kV320BatteryWithdrawn
AG1-184Carson-Suffolk 500 kV175.1BatteryWithdrawn

Sussex, VA: 39 requests in the PJM queue, 14 active totaling 1,580.7 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy800
MW capacity480
MFO800

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.