Fountain Point Solar (AE1-092) is listed in the PJM interconnection queue as a 96.4 MW solar project in Union County, OH. The filing names Blue Jacket-Kirby as its point of interconnection. PJM lists its status as “EP”, with a target commercial operation date of April 30, 2030.

Queue IDAE1-092
Project nameFountain Point Solar
Status (as published)EP
SubstationBlue Jacket-Kirby
Point of interconnectionBlue Jacket-Kirby 138 kV
CountyUnion
StateOH
Voltage138 kV
Capacity96.4 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2030-04-30
Source datasetcycle

Same substation and county

Blue Jacket-Kirby substation: 3 requests in the PJM queue, 1 active totaling 96.4 MW.

Queue IDProjectMWResourceStatus
AF2-216Blue Jacket-Kirby 138 kV90SolarWithdrawn
AF1-270Blue Jacket-Kirby 138 kV50SolarWithdrawn

Union, OH: 35 requests in the PJM queue, 6 active totaling 572.2 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperFountain Point Solar Energy LLC
Transmission ownerDayton
Project typeGeneration Interconnection
CycleTC1
StageFINAL AGREEMENT
MW energy206.55
MW capacity96.4
MFO206.55
Submitted date8/31/2018
Last updated2/20/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first