Substation Scout

Fayette Solar

PJM queue ID AE1-040

Fayette Solar (AE1-040) is listed in the PJM interconnection queue as a 31.6 MW solar project in Fayette County, OH. The filing names Greenfield as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of May 31, 2024.

Queue IDAE1-040
Project nameFayette Solar
Status (as published)In Service
SubstationGreenfield
Point of interconnectionGreenfield 69 kV
CountyFayette
StateOH
Voltage69 kV
Capacity31.6 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2024-05-31
Source datasetserial

Same substation and county

Greenfield substation: 3 requests in the PJM queue, 1 active totaling 31.6 MW.

Queue IDProjectMWResourceStatus
AI2-250Greenfield 69 kV10SolarWithdrawn
AF2-283LK-Route 1060HybridWithdrawn

Fayette, OH: 16 requests in the PJM queue, 3 active totaling 1,956.6 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy48
MW capacity31.6
MFO48

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.