Substation Scout

Foxhound Solar

PJM queue ID AD2-202

Queue IDAD2-202
Project nameFoxhound Solar
Status (as published)In Service
SubstationClover-Sedge Hill
Point of interconnectionClover-Sedge Hill 230kV
CountyHalifax
StateVA
Voltage230 kV
Capacity12.8 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2024-05-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy18.8
Mw Capacity12.8
Mfo83

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.