Steubenville Solar
PJM queue ID AD2-014
Steubenville Solar (AD2-014) is listed in the PJM interconnection queue as a 20.8 MW solar project in Jefferson County, OH. The filing names Steubenville as its point of interconnection. PJM lists its status as “Suspended”, with a target commercial operation date of December 31, 2027.
| Queue ID | AD2-014 |
|---|---|
| Project name | Steubenville Solar |
| Status (as published) | Suspended |
| Substation | Steubenville |
| Point of interconnection | Steubenville 69 kV |
| County | Jefferson |
| State | OH |
| Voltage | 69 kV |
| Capacity | 20.8 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2027-12-31 |
| Source dataset | serial |
Same substation and county
Steubenville substation: 2 requests in the PJM queue, 1 active totaling 20.8 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| AI2-072 | Steubenville 69 kV | 27.8 | Solar | Withdrawn |
Jefferson, OH: 16 requests in the PJM queue, 6 active totaling 2,070.8 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 49.5 |
| MW capacity | 20.79 |
| MFO | 49.5 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.