Jefferson, OH interconnection queue

6 active projects totalling 2,070.8 MW in the PJM queue, plus 10 with terminal status (shown greyed).

6active projects
2,070.8active MW
16total filed
Queue IDProjectkVMWResourceStatus
R68 Sammis 345kV 345 1,940 Coal Withdrawn
I07 W. H. Sammis 345kV 345 1,860 Coal Withdrawn
C01-2114 Sammis - Star 345 kV 345 850 Gas Active
C01-2121 Sammis - Star 345 kV 345 850 Gas Active
C01-2100 BROADACRE 138 kV 138 350 Battery Active
AA2-041 Tidd-Collier n/r 225 Not reported Withdrawn
AH2-126 Tidd 138 kV 138 100 Battery Withdrawn
W1-002 Tiltonsville-Windsor 138kV 138 98 Not reported Withdrawn
S123 Pike Island 138 39 Hydro Withdrawn
AI2-072 Steubenville 69 kV 69 27.8 Solar Withdrawn
AD2-014 Steubenville Solar 69 20.8 Solar Suspended
T175 Tiltonsville 69kV 69 11 Hydro Withdrawn
X2-053 Amsterdam 69kV 69 6.4 Gas Withdrawn
C01-2040 Sammis 345 kV 345 0 Battery Active
W1-078 Sammis-Wylie Ridge 345kV 345 0 Not reported In Service
W2-008 Tiltonsville-Windsor 138kV 138 0 Not reported Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.