Sweet Sue Solar
PJM queue ID AD1-105
Sweet Sue Solar (AD1-105) is listed in the PJM interconnection queue as a 44.4 MW solar project in King William County, VA. The filing names Kings Dominion DP as its point of interconnection. PJM lists its status as “Under Construction”, with a target commercial operation date of December 31, 2026.
| Queue ID | AD1-105 |
|---|---|
| Project name | Sweet Sue Solar |
| Status (as published) | Under Construction |
| Substation | Kings Dominion DP |
| Point of interconnection | Kings Dominion DP 115 kV |
| County | King William |
| State | VA |
| Voltage | 115 kV |
| Capacity | 44.4 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2026-12-31 |
| Source dataset | serial |
Same substation and county
Kings Dominion DP substation: 6 requests in the PJM queue, 1 active totaling 44.4 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| AF1-031 | Kings Dominion DP 115 kV | 60.7 | Solar | Withdrawn |
| AG1-134 | Kings Dominion DP 115 kV | 60 | Solar | Withdrawn |
| AF1-067 | Kings Dominion DP 115 kV | 30 | Hybrid | Withdrawn |
| AE2-108 | Kings Dominion DP 115 kV | 8.4 | Solar | Withdrawn |
| AE2-109 | Kings Dominion DP 115 kV | 2.9 | Solar | Withdrawn |
King William, VA: 6 requests in the PJM queue, 2 active totaling 55.3 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 74 |
| MW capacity | 44.4 |
| MFO | 74 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.