Circleville Solar Energy
PJM queue ID AC2-029
Circleville Solar Energy (AC2-029) is listed in the PJM interconnection queue as a 26.6 MW solar project in Pickaway County, OH. The filing names Circleville as its point of interconnection. PJM lists its status as “Suspended”, with a target commercial operation date of December 31, 2027.
| Queue ID | AC2-029 |
|---|---|
| Project name | Circleville Solar Energy |
| Status (as published) | Suspended |
| Substation | Circleville |
| Point of interconnection | Circleville 138kV |
| County | Pickaway |
| State | OH |
| Voltage | 138 kV |
| Capacity | 26.6 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2027-12-31 |
| Source dataset | serial |
Same substation and county
Circleville substation: 4 requests in the PJM queue, 1 active totaling 26.6 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| AH2-228 | Circleville 138 kV | 150 | Battery | Withdrawn |
| AI2-269 | Circleville 138 kV | 32.2 | Solar | Withdrawn |
| AI1-098 | Circleville 138 kV | 30 | Hybrid | Withdrawn |
Pickaway, OH: 35 requests in the PJM queue, 9 active totaling 196.9 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 70 |
| MW capacity | 26.6 |
| MFO | 70 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.