Dinwiddie 2
PJM queue ID AC1-061
Dinwiddie 2 (AC1-061) is listed in the PJM interconnection queue as a 0.2 MW hybrid project in Dinwiddie County, VA. The filing names Locks as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of June 1, 2017.
| Queue ID | AC1-061 |
|---|---|
| Project name | Dinwiddie 2 |
| Status (as published) | In Service |
| Substation | Locks |
| Point of interconnection | Locks 34.5kV |
| County | Dinwiddie |
| State | VA |
| Voltage | 34.5 kV |
| Capacity | 0.2 MW |
| Resource (as published) | Diesel; Methane |
| Resource category | Hybrid (normalized for filtering) |
| Target commercial operation | 2017-06-01 |
| Source dataset | serial |
Same substation and county
Locks substation: 3 requests in the PJM queue, 1 active totaling 0.2 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| AF2-259 | Locks 34.5 kV | 15 | Solar | Withdrawn |
| AF2-108 | Locks 34.5 kV | 10 | Hybrid | Withdrawn |
Dinwiddie, VA: 20 requests in the PJM queue, 8 active totaling 2,405.2 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 0 |
| MW capacity | 0.2 |
| MFO | 3 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.