Lee-DeKalb Wind Energy Center
PJM queue ID AB2-132
Lee-DeKalb Wind Energy Center (AB2-132) is listed in the PJM interconnection queue as a 2.2 MW hybrid project in Lee County, IL. The filing names Haumesser Road as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of September 1, 2023.
| Queue ID | AB2-132 |
|---|---|
| Project name | Lee-DeKalb Wind Energy Center |
| Status (as published) | In Service |
| Substation | Haumesser Road |
| Point of interconnection | Haumesser Road |
| County | Lee |
| State | IL |
| Voltage | Not reported |
| Capacity | 2.2 MW |
| Resource (as published) | Wind; Storage |
| Resource category | Hybrid (normalized for filtering) |
| Target commercial operation | 2023-09-01 |
| Source dataset | serial |
Same substation and county
Haumesser Road substation: 3 requests in the PJM queue, 1 active totaling 2.2 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| AE2-107 | Haumesser Road 138 kV | 54 | Solar | Withdrawn |
| Y2-048 | Haumesser Road | 0 | Battery | Withdrawn |
Lee, IL: 106 requests in the PJM queue, 30 active totaling 2,565.3 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 0 |
| MW capacity | 2.2 |
| MFO | 240 |