Sadler Solar

PJM queue ID AB2-100

Queue IDAB2-100
Project nameSadler Solar
Status (as published)In Service
SubstationClubhouse-Lakeview
Point of interconnectionClubhouse-Lakeview 230kV
CountyGreensville
StateVA
Voltage230 kV
Capacity67 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2021-12-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy100
Mw Capacity67
Mfo100