Biggs Ford Solar Facility (AB1-125) is listed in the PJM interconnection queue as a 5.7 MW solar project in Frederick County, MD. The filing names Carroll-Monocacy as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of September 1, 2025.

Queue IDAB1-125
Project nameBiggs Ford Solar Facility
Status (as published)In Service
SubstationCarroll-Monocacy
Point of interconnectionCarroll-Monocacy 34.5kV
CountyFrederick
StateMD
Voltage34.5 kV
Capacity5.7 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2025-09-01
Source datasetserial

Same substation and county

Carroll-Monocacy substation: 2 requests in the PJM queue, 2 active totaling 13.3 MW.

Queue IDProjectMWResourceStatus
AB1-124Legore Bridge Solar Center Facility7.6SolarIn Service

Frederick, MD: 34 requests in the PJM queue, 8 active totaling 923.1 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy15
MW capacity5.7
MFO15

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.