Linden 5 & 6 (A03) is listed in the PJM interconnection queue as a 120 MW gas project in Union County, NJ. The filing names Linden or as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of June 1, 2000.

Queue IDA03
Project nameLinden 5 & 6
Status (as published)In Service
SubstationLinden or
Point of interconnectionLinden 230 kV or 138 kV
CountyUnion
StateNJ
Voltage230 kV
Capacity120 MW
Resource (as published)Natural Gas
Resource categoryGas (normalized for filtering)
Target commercial operation2000-06-01
Source datasetserial

Same substation and county

Linden or substation: 2 requests in the PJM queue, 2 active totaling 870 MW.

Queue IDProjectMWResourceStatus
A04Linden 1, 2 & 3750GasIn Service

Union, NJ: 40 requests in the PJM queue, 21 active totaling 3,558.8 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy120
MW capacity120
MFO120

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.